Vestas To Supply 37 Wind Turbines For Wind Farm In South Africa

The wind power project, consisting of 37 V100-1.8 MW wind turbines, will be installed in the province of Hopefield at the Western Cape of the country.

Vestas, the world leader in wind energy, is pleased to announce a 67 MW order from Umoya Energy for South Africa.

The turbine delivery is planned for the second quarter of 2013 and the wind farm is expected to be commissioned by February 2014.

Umoya Energy is a project company with participation of the African Infrastructure Investment Fund Trust, the Kagiso Infrastructure Empowerment Fund Trust, the Infrastructural, Developmental and Environmental Assets Managed Fund, Tomlo Commodities (Pty) Ltd and the Hopefield Wind Farm Local Community Company.

Umoya Energy orders 37 V100-1.8 MW for wind farm in Hopefield

Umoya Energy is proud to be a successful REIPPP (Renewable Energy Independent Power Producer Programme) Round 1 bidder and congratulates the RSA Department of Energy for running a world-class procurement process. We are pleased to have formed a partnership with Vestas Southern Africa for the provision of EPC and O&M services on the Hopefield Wind Farm. The interactions to date have reinforced our decision and we look forward to an ongoing mutually beneficial relationship with Vestas,” says Mr Richard Gordon, CEO of Umoya Energy.

The contract includes the supply, installation and commissioning of 37 V100-1.8 MW wind turbines, along with a VestasOnline® Business SCADA solution, full scope civil and electrical works as well as a 15-year full-scope service agreement (AOM 5000). The AOM 5000 service package offers customers assured performance, helping them to avoid unforeseen operational costs of any kind.

The project contains strong local economic development obligations. Beside the supply of clean energy, it provides significant employment and skills development to the local community. In this regard, Vestas is taking its responsibilities very seriously. We are excited to contribute not only to long- term renewable energy generation in South Africa, but also to the sustainable development of the communities Vestas is working in,” states Phylip Leferink, Vice President of Sales Benelux and South Africa, Vestas Central Europe.

After being awarded ‘preferred supplier’ for several wind power projects in South Africa, today, we are very proud to receive the Hopefield order from our partner Umoya Energy,” says Dr. Wolfgang J. Schmitz, President of Vestas Central Europe. “For us, this project marks the exciting start of developing large wind power plants and several hundred MWs in South Africa over the next few years. As a pioneer in the development of the wind energy sector on this market, Vestas offers Umoya Energy 30 years of experience and leading technology wind turbines, making a clearly successful business case.”

Customer: Umoya Energy
Project name: Hopefield Wind Farm
Location/Country: Hopefield, South Africa
Number of MW: 66.6 MW
Number of wind turbines/type: 37 x V100-1.8 MW wind turbines
Contract type: Turnkey
Contract scope: The contract includes supply, installation and commissioning of the wind turbines, civil and electrical works, a VestasOnline® Business SCADA solution as well as a 15-year full-scope service agreement (AOM 5000).
Time of delivery: Delivery of the wind turbines will begin in the second quarter of 2013 and the wind power plant is expected commissioned by February 2014.

 

Every single day, Vestas wind turbines deliver clean energy that supports the global fight against climate change. Wind power from Vestas’ more than 47,000 wind turbines currently reduces carbon emissions by approximately 55 million tons of CO2 every year, while at the same time building energy security and independence. Today, Vestas have installed turbines in more than 70 countries, providing jobs for around 19,000 passionate people at our service and project sites, research facilities, factories and offices all over the world.