KACARE specified that in the first two bidding rounds after the introductory procurement round, it wanted 2.4 GW of PV solar energy capacity and 2.1 GW of concentrated solar power capacity.

Saudi Arabia has quickly made it onto the list of focus markets for investors and technology providers, with the government announcing its ambitious $109 billion plan to install 41GW of solar power and 9 GW of wind energy capacity by 2032.

Saudi Arabia has published a roadmap for its renewable energy programme, aimed at reducing the amount of oil it burns in power stations, and targets issuing final bids for the first plants within three months.

The world’s top oil exporter aims to install 23.9 gigawatts (GW) of renewable power capacity by 2020 and 54.1 GW by 2032, it said in the roadmap, which would make Saudi Arabia one of the world’s main producers of renewable electricity.

In 2012 global installed capacity for photovoltaic (PV) solar power was 100 GW.

The kingdom says it has crude output capacity of 12.5 million barrels a day, but domestic oil consumption is rising quickly and may start to cut into the amount of energy available for export.

The King Abdullah City for Atomic and Renewable Energy (KACARE), the government department responsible for the programme, last year published its vision for a long-term energy mix that relied on big contributions from solar energy.

KACARE said in its roadmap, a white paper published on Wednesday, that it aims to issue a request for prequalification for the first rewewable plants within two months, a final tender within three months and to award contracts within a year.

It said the initial contracts would be part of an “introductory” procurement round of 500-800 MW, but that it would launch two more tenders within three years for 7 GW of installed capacity.

Saudi Arabia wants most of the new renewable energy capacity to come from two solar power technologies, but is also seeking to generate electricity from wind energy, geothermal energy and waste-to-energy projects.

Renewable power developers will have 20-year contracts to sell electricity to a new government body that will in turn sell it on to the national grid.

New projects will have minimum requirements for local content and the employment of Saudi nationals, KACARE said, and developers must contribute to a Saudi research and development programme for renewable energy.

The initial tendering process for the first projects this year aims to determine the cost of installing major renewable plants in Saudi Arabia to set a pricing structure for future bidding rounds, it said.

 